6 years to go!
Time is ticking until the Brisbane 2032 Olympic Games.
When the current government was voted in in Oct 2024, they declared an end to the "Olympic chaos". They would get things back on track.
It's 18 months since their 100 day review. While they made some big announcements and changes, most notably -
● Moving the main stadium to Victoria Park
● A National Aquatic Centre at Spring Hill
● Scrapping Brisbane Live and offering up the GoPrint Site in Woolloongabba for a privately-funded indoor arena
● Moving the main Athlete's Village to the RNA Showgrounds
● Moving the GC Athlete's Village to Royal Pines
● Taking rowing to the Fitzroy River in Rockhampton
There hasn't actually been much progress at all on the ground. It's still just concept drawings being released to the public. There's no construction happening (unless you consider early works / site investigations construction).
What's happened is that, by making these changes, things have essentially been delayed by 2 years. This is because all the above has had to start again from scratch.
We now have a more concentrated construction timeline. The Qld Audit Office raised the issue last year, stating "Workforce constraints and early stage planning present delivery risks for both the capital program and Brisbane 2032 projects".
It was also pointed out by the Qld Major Contractors Association back in 2023, before the Government made the above changes.
The big problem we have is, unlike many other infrastructure projects, the Olympics needs to be delivered "on time". Given the current situation, "on time" means two things -
𝐑𝐞𝐝𝐮𝐜𝐢𝐧𝐠 𝐭𝐡𝐞 𝐬𝐜𝐨𝐩𝐞 - May happen with stadium design / size, and ancillary works like landscaping / rehabilitation or associated transport infrastructure projects may be reduced or paid out of another magic bucket of money
𝐁𝐮𝐝𝐠𝐞𝐭 𝐢𝐧𝐜𝐫𝐞𝐚𝐬𝐞𝐬 - Almost certain as work transitions to weekends and, potentially, 24/7 set-ups
With all this in mind, you would think the Government would try and keep things simple. But, in going with their choices for the main stadium, aquatic centre and main athlete's village, they've gone with locations that are extremely complex.
It's necessitated more detailed and longer preliminary investigations and design work as well as more earthworks and site establishment. They've compounded the problem, making delivery more difficult, not less.
Obviously, the idea we won't be ready in time for the Olympics seems unfathomable. But, there is a mammoth amount of work to be done from now until then.
We can forget about any semblance of sticking to the $7.1B venue or $3.5B athletes' villages budgets, despite the Government's continued insistence.