08/11/2025
Not posted in a while but we’ve been busy. We recently completed this important project during half term at Infocus site in Exeter. They have had multiple issues with the existing soak away design and drainage caused numerous flooding events at this school. We were able to work with the Estates team to get solution and plan the works.
We completed the works in 8 days over half term period minimising disruption using the main drop off/ pickup area.
Work included a new 3m deep attenuation chamber, replacement of 40LM of new drainage, new road spec Inspection chamber, silt trap unit, topsoil & tarmac reinstatement works.
Thanks to our guys that worked on the challenging project and enabled us to complete on time.